Overview:
At the Oct. 12, 2026 meeting, the City of New Hope will present the feasibility report for the proposed 2027 Infrastructure Improvement Project. A public hearing will then be held on Oct. 26, 2026.
A map of affected streets is available at the link below.
The project map shows two types of street repairs. Streets will get a reclaim and overlay, which means the old pavement is completely removed down to the gravel base. Roads will be gravel for a couple of weeks while repairs are made, then new pavement will be added.
Schedule:
The project will begin in spring 2027 and will be completed by fall 2027. Work will take place from Monday to Friday, between 7 a.m. and 8 p.m., with occasional work on Saturdays from 9 a.m. to 6 p.m.
Project Contact:
Nick Macklem, Project Coordinator
Phone: 763.592.6765
Email: [email protected]